#### 51. Configuration management is best described as:
الإجابة: d. creation, maintenance and controlled change of the project deliverables.
---
#### 52. A Cost Breakdown Structure (CBS) shows costs assigned to:
الإجابة: a. individual work packages using the Work Breakdown Structure (WBS).
---
#### 53. The accuracy of an estimate should:
الإجابة: b. increase as a project progresses through its life cycle.
---
#### 54. Which one of the following best defines a benefit?
الإجابة: c. An improvement resulting from project deliverables.
---
#### 55. Which one of the following is true for the Project Management Plan (PMP)?
الإجابة: d. The Project Management Plan is developed by the project manager and team and owned by the project manager.
---
#### 56. Who are project team members primarily accountable to?
الإجابة: d. The project manager.
---
#### 57. The phases of a project life cycle are:
الإجابة: b. concept, definition, development, handover and closure.
---
#### 58. A portfolio can best be defined as:
الإجابة: a. a group of projects and programmes carried out within an organisation.
---
#### 59. Which one of the following best describes project management?
الإجابة: d. Application of processes and methods throughout the project life cycle.
---
#### 60. Which structure shows the reporting relationships and communications channels for a project?
الإجابة: b. Organisational Breakdown Structure.
---
#اسئلة مع الحل
#اساسيات_مشاريع_تكنولوجيا_المعلومات
#للفائدة
#مشاركة_من_احد_طلاب_الدفعة
الإجابة: d. creation, maintenance and controlled change of the project deliverables.
---
#### 52. A Cost Breakdown Structure (CBS) shows costs assigned to:
الإجابة: a. individual work packages using the Work Breakdown Structure (WBS).
---
#### 53. The accuracy of an estimate should:
الإجابة: b. increase as a project progresses through its life cycle.
---
#### 54. Which one of the following best defines a benefit?
الإجابة: c. An improvement resulting from project deliverables.
---
#### 55. Which one of the following is true for the Project Management Plan (PMP)?
الإجابة: d. The Project Management Plan is developed by the project manager and team and owned by the project manager.
---
#### 56. Who are project team members primarily accountable to?
الإجابة: d. The project manager.
---
#### 57. The phases of a project life cycle are:
الإجابة: b. concept, definition, development, handover and closure.
---
#### 58. A portfolio can best be defined as:
الإجابة: a. a group of projects and programmes carried out within an organisation.
---
#### 59. Which one of the following best describes project management?
الإجابة: d. Application of processes and methods throughout the project life cycle.
---
#### 60. Which structure shows the reporting relationships and communications channels for a project?
الإجابة: b. Organisational Breakdown Structure.
---
#اسئلة مع الحل
#اساسيات_مشاريع_تكنولوجيا_المعلومات
#للفائدة
#مشاركة_من_احد_طلاب_الدفعة
👍2
ملاحضات على باقي chapter_5 (1).pdf
914.5 KB
ملاحضات على باقي chapter_5.pdf
نماذج ادارة مشاريع.pdf
412.8 KB
مشاركة نماذج ادارة مشاريع.pdf
نموذج_اختبار_نصفي_للدكتور_نبيل_الصهيبي.pdf
284.2 KB
نموذج اختبار نصفي للدكتور نبيل الصهيبي.pdf
Test bank PM DONE by HAMZA KOBBAN.pdf
838.3 KB
Test bank PM DONE by HAMZA KOBBAN