تكنولوجيا المعلومات مستوى ثالث | جامعة صنعاء – Telegram
تكنولوجيا المعلومات مستوى ثالث | جامعة صنعاء
3.23K subscribers
1.14K photos
260 videos
2.4K files
742 links
💢القناة الرئيسية💢
https://news.1rj.ru/str/USF_Computer2_IT_10 ⬅️
💢مجتمع الدفعة IT3💢
https://news.1rj.ru/str/USF_IT_2024_COMMUNITY ⬅️
💢 قناة الأسئلة 💢
https://news.1rj.ru/str/hchgrcu ⬅️
بوت التواصل والمشاركة والإقتراحات
@Technologyhbot ⬅️
Download Telegram
ياجماعة الخير توكلوا على الله
ولا تقلقوا ومن توكل على الله
ماخاب ، خليكم مرتاحين البال
وما كتبه الله لنا يامرحبا به .
🫡14🕊51💯1
Which of these is not one of the constraints of a project?
Anonymous Quiz
11%
Scope
15%
Resources
38%
Team
36%
Budget
🫡3👍2
Which of the following types of Organizational Charts can be BEST used to track project costs:
Anonymous Quiz
24%
Hierarchical-type Organizational Chart
39%
Organizational Breakdown Structure
19%
Resource Breakdown Structure
18%
Responsibility Assignment Matrix
🫡4
The process of scoping, planning, staffing, organizing, and controlling the development of an acceptable system at a minimum cost within a specified time frame is:
Anonymous Quiz
44%
Project Management
20%
Process Management
23%
Expectations Management Matrix
13%
Statement of Work
🫡7💯1
A narrative denoscription of the work to be performed as part of a project is:
Anonymous Quiz
20%
Scope statement
22%
Statement of work
11%
Project definition
48%
All of these
🫡5
Which of the following is considered a project resource?
Anonymous Quiz
19%
People
12%
Services
17%
Facilities
53%
All of these
🔥3👍1
Which of the following is NOT an output of the develop schedule process?
Anonymous Quiz
12%
Project schedule
13%
Schedule baseline
17%
Schedule data
58%
Resource breakdown structure
🫡3
Which process results in the project funding requirements document as one of its outputs?
Anonymous Quiz
24%
Estimate activity resources
16%
Estimate activity durations
28%
Estimate costs
32%
Determine budget
هولاء الاسئله مهمين جدا دورت لهن من موقع وشفت ان اغلب اختبارت الدكتور السابقه من نفس الموقع
🫡14👍2🔥2
During project executing, a team member comes to the project manager because he is not sure of what work he needs to accomplish on the project. Which of the following documents contain detailed denoscriptions of work packages?
Anonymous Quiz
47%
WBS dictionary
14%
Activity list
25%
Project scope statementProject scope statement
14%
Scope management plan
👍1
Which is normally not regarded as an element of cost of quality?
Anonymous Quiz
16%
Prevention costs.
31%
Maintenance costs.
26%
Appraisal costs
27%
Failure costs.
👍2🕊2
You have been criticized that certain specifications in your scope statement do not pass the test for SMART objectives. What are SMART objectives?
🔥2🤔2
What is a common result of poor project planning?
Anonymous Quiz
12%
Wasted effort
12%
Lost time
10%
Increased cost
66%
All of the above
👍1🤩1
Which of the following aspects of planning has the most processes and is concerned with decomposing the work of a project into manageable portions?
Anonymous Quiz
37%
Scope
21%
Time
10%
Cost
31%
Quality
👍1🤩1
You are a project manager newly assigned to a large project for your organization. The project charter has been signed, and the stakeholders have been identified. What should you do next?
Anonymous Quiz
24%
Ask appropriate team members to submit WBS input
36%
Initiate the scope planning process
34%
Start the develop project management plan process
6%
Begin the activity definition process